fbpx

Work starts epic year-long HS2 viaduct deck slide

HS2 main works contractor EKFB has started a year-long bridge slide to push almost half a kilometre of deck into position high above the Misbourne Valley in Buckinghamshire.

The Wendover Dean Viaduct will be the first major railway bridge in the UK to be built with a ‘double composite’ approach.

The increased strength of the steel/concrete composite deck design allows it to slid over the viaduct piers in an epic push of 90 to 180m long sections.

Wendover Viaduct deck from above during the first deck slide looking south

This critical new stage of construction will see sections pushed out in sequence from the north abutment across teflon pads.

With each new section being attached behind the other, the weight of the deck will increase with each push, up from an initial 590 tonnes this week to 3,700 tonnes by the end of the year.

Deck beam at dusk as the first day of the Wendover Dean deck slide came to an end

James Collings, EKFB’s senior engineer, said: “The project team has reached a fundamental milestone in the build of this industry-leading viaduct.

“We’re progressing well with the first-of-three steel launches being conducted this year and already looking forward to seeing this viaduct come to life. Along with our supply chain partners, Eiffage Metal, we’re proud to be delivering this viaduct safely and to programme.”

Tomas Garcia, HS2 Ltd’s Head of Civil Structures said: Double composite structures maximise the combined strength of steel in tension and concrete in compression. This approach has been tried and tested around the world and it’s great to see it applied on this scale for the first time in the UK at Wendover Dean.”

Composite deck carbon savings

View of the underside of the Wendover Dean Viaduct showinhg the double composite structure

Instead of using solid pre-stressed concrete beams to form the spans between the viaduct piers, the ‘double composite’ structure uses two steel beams sandwiched between two layers of reinforced concrete to create a lightweight and super strong hollow span.

EKFB worked with their design partner, ASC (a joint venture between Arcadis, Setec and COWI) and architects Moxon on the ‘double composite’ approach which was inspired by structures on the French high speed TGV network.

The approach is set to cut the carbon footprint of the structure by 56% – saving almost 13,000 tonnes of embodied carbon – and helping HS2 achieve its goal of halving the amount of embedded carbon in construction.

Deck beam slid into position with deck slabs and balancing ponds behind

Generated by Feedzy